Direct Connection / Direct Connection within the Premises in Dehiwala, Ratmalana, Moratuwa, Colonnawa, Ja-Ela and Ekala Area.


Project Summary

Contract No : PD/GPOBA/DC/2012/01
Date of Award : 21.12.2012
Contractor : Squire Mech. Engineering (Pvt.) Ltd.
Contractor : 730 Days (2 years)
Contract Period : 18.01.2013
Date of Commencement : 03.01.2015
Intended Date of Completion : 03.01.2015
Actual Date of Completion : 03.08.2015 (extension granted))
Progress
Physical Progress : 100%
No of Connections Completed under output type 1a1 : 898
No of Connections Completed under output type 1a2 : 236
Financial Progress : 100%
  • 1a1 :Direct Connection Full Cost Build out
  • 1a2 : Direct Connection Within Premises

Direct connections are organized under two categories, distinguishing “Direct Connection full Cost Build out (1a1)” from “Direct Connection Within the Premises (1a2)”. Construction of Interceptor Manhole, connection to existing lateral or manhole and connecting of grey and black water of household through catch pits to the interceptor shall be done under the full cost build out connections and connecting of grey and black water of household through catch pits to the interceptor shall be done under the direct connection within the premises.

Under this sub project targeted to increase the household access in Dehiwala / Mt.Lavinia, Kolonnawa, Ja-Ela / Ekala and Moratuwa / Ratmalana project area by providing sewerage connections to poor community who are living close to existing sewerage networks. Beneficiaries are selected on the basis of their monthly income and area of land available for the setup of the units. Though the communication campaign activities such as awareness programs, meetings, leaflet distribution etc. will be done to make the community aware about this project and increase the beneficiaries under this project. Selection of beneficiaries will be done with the additional assistance of the relevant local authorities.

-->